Maintenance Dredging of New York and New Jersey Harbor – Arthur Kill 50 foot Reach Federal Navigation Project
At a glance
Maintenance Dredging of New York and New Jersey Harbor – Arthur Kill 50 foot Reach Federal Navigation Project is a federal contract from W2SD ENDIST NEW YORK (DEPT OF DEFENSE), in US. Responses are due 2 Dec 2026. It was posted 17 Nov 2026. The solicitation number is W912DS27S0009. Its NAICS code is 237990. The buyer's notice has the documents and how to respond.
Overview
- Buyer
- W2SD ENDIST NEW YORK (DEPT OF DEFENSE)
- Place
- US
- Type
- Federal contract
- Solicitation number
- W912DS27S0009
- Status
- Open
Key dates
- Posted
- 17 Nov 2026
- Responses due
- 2 Dec 2026
- Time and time zone
- Not stated. Check the buyer's notice.
Summary
The buyer's description, as posted.
Market Survey Background Information The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of the New York and New Jersey Harbor - Arthur Kill 50 foot Reach Federal Navigation Project to a depth of -50 feet Mean Lower Low Water (MLLW) plus 1 foot of allowable over-depth. The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of material from the critical shoal area. The dredged material would be dredged and subsequently placed at a suitable, contractor provided, state permitted upland placement site(s). The dredged material is expected to consist primarily of silt, clay, and some sand. Based on the past dredging projects within the New York Harbor, and anticipated restrictions found in the New York State Department of Environmental Conservation Water Quality Certificate, the proposed work can only be performed by utilizing a mechanical clamshell dredge with environmental bucket. Additionally, tug-boats, sealed hull barges and survey vessels will be needed to perform the work during the dredging, transport, processing and placement activities. The dredging, transport and placement at a suitable, contractor provided, state permitted upland placement site(s) would be required to meet all federal, state, and local criteria required by the government agencies having jurisdiction where the dredging and placement sites are located. All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the Notice to Proceed and maintain an integrated production rate of at least 3,000 cubic yards per calendar day for the dredging and placement of the dredged material. The presence of the dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact. The proposed work is anticipated to take place in the summer / fall of 2027. SURVEY OF THE DREDGING INDUSTRY The following confidential survey questionnaire is designed to apprise USACE of prospective dredging contractors' project execution capabilities. Please provide your response to the following questions. All questions are in regard to the Arthur Kill 50 foot Reach maintenance dredging project. General 1. Have you ever worked on dredging jobs similar in nature to this project? If so, please describe the project and for whom the work was performed. Identify a point of contact and phone number, as a reference of relevant experience. 2. Have you performed dredging within the waters of the Port of New York and New Jersey? 3. Do you have experience with the placement of dredged material at a suitable, contractor provided, state permitted upland placement site? Please list your experience. 4. What percentage of work (volume of material dredged, transported, processed and ultimately placed) can you perform with your own equipment or equipment owned by another dredging contractor? 5. Would you be willing to bid on the project previously described? If the answer is No, please explain why not. 6. Would you be bidding on this project as a sole contractor, prime contractor with subcontractor(s) or as a joint venture? 7. Is there a dollar limit on the size of contract that you would bid? If so, what is that limit? 8. What is the largest dredging contract, in dollars, on which you were the prime contractor? 9. What is your bonding capacity per contract? What is your total bonding capacity? 10. Do you…
Shortened here. The full text is in the buyer's notice.
Requirements
- NAICS code
- 237990
- Product or service code
- Y1KF
Official notice
The buyer's own page for this bid, with its documents and any changes.
Related open bids
Due27 Nov 2026
Due27 Nov 2026
Due27 Nov 2026
Due27 Nov 2026
Due27 Nov 2026
Due27 Nov 2026
Due27 Nov 2026
Due27 Nov 2026
Pursue it in Capveon
Read the documents, check the requirements against your team and draft the response in one place.